Temporary power supplier Aggreko is working with Duro Felguera, a specialist geological exploration group from Spain dedicated to developing and executing projects for a number of industrial sectors, including oil and gas. Aggreko is to provide power for Duro Feguera’s research work into natural gas fields in Santo Antonio dos Lopes, in the state of Maranhao, Brazil.

Duro Felguera was commissioned to explore areas of Santo Antonio dos Lopes where grid power was not available. As the search for natural gas requires the use of heavy machinery with large motors that require reliable power, Aggreko was asked to provide 12 generators of various sizes (between 125 kVA and 500 kVA), capable of producing 3.1 MW of power.
Meanwhile, Aggreko has been chosen by one of Brazil’s largest independent renewable power generation companies to conduct performance tests at the Morro do Ventos wind farms in the northeast of the country.
The UK firm will supply load banks – a recreation of the load that a power source will generate – for commissioning tests of the 145 MW wind farms, which are operated by Dobreve Energia. Load bank testing ensures that the wind farm is ready for grid connection.