Regulators in BESS safety review warning after US explosion

Fri, 05/17/2019 - 09:38 -- John Shepherd
Regulators in BESS safety review warning after US explosion

Regulators in the US have warned a major shake-up of safety standards may be needed for home battery storage systems in the wake of an explosion at a lithium-ion grid-scale battery storage facility in Arizona.

The Arizona Public Service (APS) utility told BEST Battery Briefing an investigation into what caused the “catastrophic failure” of the 2MW/2MWh system at its McMicken facility last month in the city of Surprise was still under way.

The full story is only available in our FREE weekly industry newsletter, so sign-up to get it delivered to your inbox every Monday.

Probe launched into Arizona BESS explosion

Tue, 04/23/2019 - 17:44 -- John Shepherd
Probe launched into Arizona BESS explosion

An investigation is under way after an explosion at a lithium-ion grid-scale battery storage facility in the US operated by the Arizona Public Service (APS) utility.

APS told BEST Battery Briefing today several firefighters and a police officer needed hospital treatment as a result of the “catastrophic failure” of the 2MW/2MWh system at its McMicken facility in the city of Surprise, Arizona.

Firefighters were called to the site after smoke was discovered at the site on 19 April, an APS spokesperson told BBB. The explosion occurred about three hours after first responders arrived.

The full story is only available in our FREE weekly industry newsletter, so sign-up to get it delivered to your inbox every Monday.

US urged to end ‘uncertainty’ over battery storage tax breaks

Tue, 08/07/2018 - 12:43 -- John Shepherd
US urged to end ‘uncertainty’ over battery storage tax breaks

Treasury chiefs in the US have been urged to “end the uncertainty” over proposed tax breaks for companies rolling out energy storage projects.

The director for global market applications at US multinational Fluence, Kiran Kumaraswamy, told a US House Subcommittee on Energy hearing that battery storage developers are still waiting for guidance from the Inland Revenue Service (IRS).

The full story is only available in our FREE weekly industry newsletter, so sign-up to get it delivered to your inbox every Monday.

120 MW BESS partnership deal for UK

Fri, 06/22/2018 - 09:41 -- Xuan Zhong
120 MW BESS partnership deal for UK

US-based multinational Fluence is partnering with UK Power Reserve to commission the first phase of a 120-megawatt portfolio of battery storage facilities in the UK.

UK Power Reserve said the agreement with Fluence— a Siemens and AES company— “represents the single largest energy storage portfolio transaction with one technology provider announced in the UK to date”.

 

The full story is only available in our FREE weekly industry newsletter, so sign-up to get it delivered to your inbox every Monday.

First grid scale storage system in India

Mon, 01/29/2018 - 10:38 -- News Editor
First grid scale storage system in India

AES and Mitsubishi Corporation are to build India’s first utility-scale energy storage system, a 10MW solution that will serve the electric grid operated by Tata Power.

The companies will own the ‘Advancion’ storage solution, which is being supplied by Fluence. Once completed later this year, the system will enable better peak load management, add system flexibility and enhance reliability for more than seven million customers in the Delhi region, the firms said.

 

The full story is only available in our FREE weekly industry newsletter, so sign-up to get it delivered to your inbox every Monday.

100MW goal begins with Europe’s biggest Li-ion ESS

Fri, 02/13/2015 - 13:27 -- Paul Crompton
100MW goal begins with Europe’s biggest Li-ion ESS

Europe's biggest electricity storage battery using a 10MW lithium-ion battery array is being built in Northern Ireland (NI).

Plans to provide an extra 250MW of capacity - enough to power 160,000 homes - are in the advanced stages at a site next to Kilroot Power Station.

The full story is only available in our FREE weekly industry newsletter, so sign-up to get it delivered to your inbox every Monday.

AES to build 100MW battery storage plant in Northern Ireland

Fri, 04/04/2014 - 11:36 -- Tildy Bayar
AES to build 100MW battery storage plant in Northern Ireland

US energy storage firm AES is to build a 100MW battery energy storage plant at Northern Ireland’s biggest power station.


AES plans to build the facility at the Kilroot 660MW coal/oil power plant in Carrickfegus. The company has submitted a connection application to System Operator Northern Ireland (SONI), which operates the electricity grid in Northern Ireland.


Depending on "a suitable commercial agreement", AES could have the facility operational early in 2015.


“Leveraging existing AES infrastructure will allow us to rapidly deliver reliable, economical power resources,” John Zahurancik, vice president of AES’s energy-storage unit, said in a statement. “Storage arrays have the unique ability to participate as active power-system support with no emissions and to provide both supply and load to help manage the variability of renewables.”